Coming soon in Brickell, Miami, FL
Smart Brickell III
885 SW 3 Avenue, west Brickell, City of Miami
The completed first phase is one building holding three legally separate condominiums, and ten floors plus the garage belong to none of them. Not one of its 125 units carries a homestead exemption. The whole record is below.
- Address
- 885 SW 3 Avenue
- Area
- Brickell, Miami
- Tax rate
- 19.9544 mills
- Flood zone
- X, no elevation
At a glance
Smart Brickell III fast facts
Every figure below is read from the state condominium filings, the county appraiser's own per-folio tax tool and legal descriptions, the city permit record, the federal flood and claim files, or the county's hazard layers with controls proving each result. Where a number does not exist yet we say so plainly.
- Record address
- 885 SW 3 Avenue, Miami, FL 33130
- Filed as
- Smart Brickell III Condominium
- Area
- West Brickell, City of Miami
- Status
- Full vertical permit issued, no completion
- Tax rate
- 19.9544 mills, outside the downtown district
- What the downtown district would add
- 0.3800 mills, about $149 a year
- Non-ad-valorem on a unit
- $0.00, with two non-zero controls
- Flood zone
- X, no base flood elevation
- Evacuation zone
- B, unlike the tower a mile north
- Homestead in phase one
- Zero units of 125
- Phase one structure
- One building, three condominiums
- Homestead saving here
- About $851, or 10.88 percent
- Pricing and release dates
- Not published yet
- Association dues and reserves
- Not a public record at any stage
Not published yet
Not published yet
Location: see 885 SW 3 Avenue on the map. Figures carry the dates shown and are subject to change.
What you are actually buying into
One building, three condominiums, and ten floors that belong to none of them
To understand what is being sold here you have to look at what the same sponsor already finished a block away, because the structure is the product. The completed first phase is one physical tower containing three legally separate condominiums, divided by air rights. The appraiser's own legal descriptions carve it into a lodging condominium on floors two to seven with fifty units, a residential condominium on floors eleven to twenty-three with fifty units, and a commercial condominium on the first and twenty-fifth floors with twenty-five.
Then there is the part that belongs to nobody. Floors eight to ten and the garage are not in any of the three condominiums. They sit on their own folio, still owned by the developer's entity, taxed as a parking lot, about 54,765 square feet with a building value of about $4,217,111. Ten floors in the middle of a residential tower, privately held by the sponsor after the rest of the building has been sold.
That has a consequence in the post-Surfside law that we did not expect to find. The reserve study provisions expressly exclude any portion of a building not submitted to the condominium form of ownership. So no structural integrity reserve study can ever reach that podium. The bottom third of the tower sits outside the reserve regime the whole state has spent five years building. Who funds its structural maintenance, and on what timetable, is a contractual question rather than a statutory one, and the answer lives in a shared-facilities agreement we could not locate in any public record.
The naming tells you this is coming, if you know to read it. The second phase is filed as a condominium within a portion of a building, which is phrasing the statute compels where a condominium occupies only part of a structure. It is a warning label. Sixty-three filings statewide carry it, thirty-eight in this county, and only nine have ever recorded. The third phase, this one, currently carries one filing rather than three, but that tells you nothing: the first phase's three declarations were recorded on a single day.
One more sequencing fact from the first phase that most buyers would find startling. The condominium legally existed about eight months before the building did. The declarations recorded and all hundred residential and lodging units conveyed on the same day, and the certificate of occupancy followed the next spring. That is lawful and ordinary in Florida. It also means the turnover trigger, which fires when ninety per cent of units are conveyed, was met before anyone could move in.
Which produces the finding that should shape your questions. Selling out on day one means turning over on day one. Majority control of that association was due to pass to the owners before the building had a certificate of occupancy, and nothing in the turnover provisions requires the developer to fund the reserve gap. A brand new association took the building, and whatever the reserve schedule said it would need, the owners were the ones funding it.
Take these four to the sales office: whether this phase will be carved into more than one condominium and how; what happens to the podium and the garage, who owns them and who pays to maintain them; the shared-facilities and cost-sharing agreement between the condominiums, in writing; and the expected turnover date relative to the certificate of occupancy.
What this actually costs
A Brickell address that is not in the Brickell taxing district
The headline here is a boundary, and it runs the buyer's way for once. Downtown and Brickell normally sit inside a downtown development district that levies an extra 0.3800 mills. These parcels are about 800 to 1,100 feet west of the published boundary and return no hits against it, while a downtown control returns one. We confirmed it a third way by subtracting two per-folio tax totals, which produces exactly 0.3800.
So the rate is the plain city rate. Total 19.9544 mills rather than 20.3344: county at 5.2489, city at 7.1080, city debt at 0.2536, school board at 6.6230, children's trust at 0.4638 and four water and navigation levies totalling about 0.257. On the median unit that boundary is worth about $149 a year, which is small but it is the kind of thing nobody checks and everybody assumes the wrong way round.
The non-ad-valorem line is zero and we did not take it on trust. A City of Miami condominium unit here pays $0.00 in non-ad-valorem assessments, confirmed against two controls that do carry charges. That matters more than usual on this page because two of our other Miami pages turned up non-zero lines where the county-wide rule said there would be none, so the zero is worth proving each time rather than assuming.
Now the full annual figure, which is the lowest on any Miami page we have built. On the median unit value in the completed first phase, about $391,810, the bill is about $7,818.33 without homestead and about $6,967.38 with it. That is a genuinely accessible price point for Brickell, and it is the reason this scheme exists.
At that value the homestead exemption finally does real work. About $850.96 of saving on a bill of about $7,818 is 10.88 per cent, against 3.48 per cent on an Edgewater tower unit and 1.77 per cent on a barrier-island unit. The exemption is a flat dollar amount, so the cheaper the unit the more it matters. If you intend to actually live in the unit, this is the price band where that decision pays.
The usual arithmetic warning applies and it is worth repeating. The second homestead exemption does not reach school levies. Applying a flat fifty thousand to every levy overstates the saving by about $146.76. We verify that against the roll's own exemption fields on every page rather than asserting it.
One valuation oddity from the first phase that will confuse anyone reading comparables. In the same building, on the same closing day, the lodging units now assess at about 0.845 times their purchase price while the residential units assess at about 1.174 times. Same structure, same date, a forty per cent spread in how the market and the assessor have treated the two products since. If somebody quotes you a price per square foot for this building, ask which condominium they took it from.
And one commercial figure worth deflating. The commercial condominium's reported sellout of about $53.4 million appears on the roll at about $4.8 million, with all twenty-five units conveyed on one day and every one flagged as between affiliated parties. The defensible residential and lodging sellout for that tower is about $43.1 million across a hundred units. Treat any aggregate sellout number in this scheme as marketing until you have seen the deeds behind it.
The practical version: the tax on this address is low by Miami standards, computable to the dollar, and slightly better than a buyer would guess because of the district boundary. The association side is unknowable from outside and, in a building with a privately held podium and three separate associations, is the part that deserves all of your attention.
The compliance clock
The reserve law has a hole in it, and this building's design puts ten floors inside the hole
Since the Surfside collapse Florida has built a hard timetable around structural inspection and reserve funding. A new building sits at the start of it, which is the usual argument for buying one. Here there is a complication that is specific to how this sponsor builds, and it is the most important thing on this page.
Start with the ordinary clocks. A building of this type falls due for its first milestone inspection, a structural review the state now compels, at thirty years from its certificate of occupancy, or twenty-five where the local building official elects the coastal trigger. The first structural integrity reserve study runs ten years from the condominium's creation, and this condominium has not been created because the declaration is unrecorded. On expected timing that puts the first milestone in the late 2050s.
Now the hole. The reserve study provisions exclude any portion of a building not submitted to the condominium form of ownership. In the completed first phase, floors eight to ten and the garage were never submitted. They are the developer's own folio, taxed as a parking lot. So the reserve study obligation cannot reach roughly a third of the structure, and the inspection regime that the entire state rebuilt after a parking structure failed has nothing to say about that podium.
We are not alleging anything improper. It is lawful, and air-rights division is a normal way to finance a mixed-use tower. What it means for a buyer is concrete: the money to maintain that part of the building comes from a private agreement rather than from a statutory reserve, and we could not find that agreement in any public record. Ask for it by name.
The turnover finding is the same everywhere and is consistently misunderstood. At turnover the developer must deliver an accountant's audit, two sealed engineering reports and the reserve study. There is no obligation anywhere in that section to fund the reserve at any level, and none to make good a shortfall. In this scheme that has already happened once, at speed, on a building that turned over before it had a certificate of occupancy.
And here is what a buyer cannot see before contracting. The record-access right that produces reserve studies, budgets and inspection reports runs to unit owners. The estoppel certificate runs to an owner, a mortgagee or their designee. A prospective purchaser is none of those. On a developer sale you get the prospectus and the condominium documents, and that is the channel that works. Use it inside your rescission window.
One thing worth knowing about how long this sponsor takes. Across the three towers, the time from plan acceptance to permit issue ran about 1,638, 1,419 and 954 days, a mean of roughly three and two thirds years. Marketing dates on this scheme have run about four years ahead of reality: the third tower was advertised for completion in 2024 and the second for closings in 2025, and neither has a certificate of occupancy today. Budget accordingly, and get the delay provisions of your contract read.
A code note that cuts in this building's favour. The completed first tower was designed under the building code edition that was current when its plans were accepted, ten days before the next edition took effect. This third phase runs under a code two editions newer. On a Miami tower that is not a trivia point, it is the wind and water detailing the structure is actually built to.
What to demand in writing before your rescission period closes: whether this phase is one condominium or several; the ownership and maintenance responsibility for the podium and garage; the shared-facilities and cost-sharing agreement; the proposed budget with its reserve schedule; the expected turnover date relative to the certificate of occupancy; and the contract's delay provisions, given this sponsor's record on timing.
Get notified when the declaration records
That document will tell you how many condominiums this tower is really split into.
The area
Zone X but an evacuation zone anyway, and a completed building with zero homesteads
The hazard picture here is mixed in an instructive way. The parcels are in flood zone X with no base flood elevation, on an effective panel dated 2009, and they are not in the coastal high hazard area, carry no coastal A or wave action designation, and take no surge at any category. On flood, this is a good address.
But it does carry an evacuation zone, and that is the nuance. This site is in hurricane evacuation zone B, a category two zone, where the Wynwood tower we studied a mile and a half north carries no evacuation zone at all. Evacuation zones and flood zones answer different questions. One asks whether water reaches the building in a storm, the other whether the area should empty out ahead of one. A building can be clean on the first and still be ordered out on the second.
The postcode claim record splits wind from water cleanly. This postcode has 178 federal flood insurance claims and about $2.80 million paid, of which 123 were rated in the mandated hazard zone and only ten outside it. Against that, 6,824 federal assistance registrations and about $2.55 million paid, of which only about $55,468 was attributed to flood at all. About 91 per cent of those registrations came from renters and about 98.7 per cent carried no flood insurance.
Read that as an instruction. The flood losses here are concentrated in the mandated zone, which this parcel is not in, and the household damage is overwhelmingly wind. Design wind speed is a countywide constant of 175 miles per hour in the high velocity hurricane zone, so the variable that matters is the code generation, and this phase is being built to a newer one than the finished tower next door.
On schools the assignment is clear with one caveat worth naming. All three sites assign to a preparatory elementary covering pre-kindergarten through eighth grade, and to Booker T. Washington Senior High in Overtown. The county's own elementary and middle boundary layers disagree with each other for grades six to eight. That is a genuine conflict in the published data, so confirm the middle-school assignment with the district rather than with either layer.
Ownership in the finished phase is the number that decides whether this is for you. Of 125 unit folios, zero carry a homestead exemption. Between 84 and 86 per cent are held by limited liability companies. Two other Brickell buildings we ran as controls the same day came back at 15.6 per cent and 24.8 per cent homesteaded. Part of the zero is structural, since the fifty lodging units legally cannot be homesteaded. The rest is not.
Be clear-eyed about what that means rather than alarmed by it. This is a short-stay and investor product wearing a residential label, and the building will be run by people optimising yield rather than by people living there. For an investor that is the whole appeal, and the price point and the ten-plus per cent homestead value make the resident case real too. But if you are buying to live in it, walk the finished tower at ten on a weekday night before you decide, and read the rental provisions in the declaration first.
What you need to know
Buying pre-construction with someone on your side
Representation costs you nothing and the timing is the catch: in a pre-construction sales gallery your agent generally has to be with you or named at your very first contact for the registration to stand. Sort it out before you call.
The case for it here is unusually concrete. This sponsor builds one tower as several condominiums and keeps a piece of the structure outside all of them. Working out which condominium your unit is in, who owns the floors underneath it, and who pays to maintain them is not a question a brochure answers. It is answered by the declaration and by a shared-facilities agreement, and somebody needs to ask for both by name.
Know what the statute gives you. On a developer sale you are entitled to the prospectus and the condominium documents, and you have a rescission right measured in days from the later of signing or delivery. On a scheme with this much structural complexity, that window is the only time anyone will read the documents for you with leverage.
On deposits the protection is narrower than most buyers assume. The first ten per cent is held in escrow. Above ten per cent the statute permits the developer to use the money for construction once work has begun, and a full vertical permit has been issued here. We did not search Florida regulatory enforcement records or civil dockets for any builder, developer, contractor or land-holding entity, so read the absence of any such note as unchecked, not clean.
The rest is specific to this building: get an independent inspection of your unit before closing and use the one-year window afterwards while the developer is still responsible. Ask what design wind speed and opening protection the plans are sealed to and which code edition governs. Ask whether your unit is in the residential condominium or the lodging one, because it changes your financing, your insurance, your tax treatment and whether you can homestead at all. And read the limited warranty before you sign.
Subdiview is not affiliated with, endorsed by, or sponsored by Smart Corner, any homebuilder, any developer of Smart Brickell III, the City of Miami, or Miami-Dade County. The developer is identified here because it is the developer of record in the state condominium filing, which is a statement of fact and not a representation of any relationship. Community names and marks are the property of their respective owners and are used for identification only. Subdiview is operated by a real estate broker licensed in Illinois. We are not your agent, we do not represent you, and we perform no real estate brokerage services in this state. No one at Subdiview is licensed in this state. If you join an interest list, your information is referred to a real estate professional licensed in the state where the property is located, who will contact you directly. We are compensated by that professional's brokerage, not by you. Pricing, plans, inventory, district, tax, flood and approval details on this page carry the dates shown, are as published, proposed or reported rather than committed, and are subject to change without notice.
Questions and answers
Smart Brickell III FAQ
What is Smart Brickell III, and what is the address?
It is the third phase of a small local developer's scheme in west Brickell, City of Miami. The record address is 885 SW 3 Avenue, and the site spans three adjoining parcels totalling about 22,500 square feet on SW 9 Street. It is filed with the state under the legal name Smart Brickell III Condominium, which is the name that will appear on your deed, and the developer of record is Smart Corner. A full vertical construction permit was issued in the summer and is active, with no certificate of occupancy.
What is unusual about how this developer builds?
The completed first phase is one physical building containing three legally separate condominiums, divided by air rights. The appraiser's own legal descriptions carve it into a lodging condominium on floors two to seven, a residential condominium on floors eleven to twenty-three, and a commercial condominium on the first and twenty-fifth floors. Floors eight to ten and the garage belong to none of the three: they sit on their own folio, still in the developer's name, taxed as a parking lot. Understand that structure before you buy into a later phase, because nothing on a brochure will tell you about it.
Why does the filing name sound so strange?
Because the statute requires it. Where a condominium occupies only part of a building, the law compels the name to say so, which is why the second phase is filed as a condominium within a portion of a building. It is effectively a statutory warning label. Sixty-three filings statewide carry that phrasing, thirty-eight of them in this county, and only nine have ever recorded. If you see it on a filing you are looking at, read the declaration's shared-facilities arrangements very carefully.
Is this in the downtown taxing district?
No, and that is worth money. Brickell is normally inside the downtown development district, which levies an extra 0.3800 mills. These parcels sit about 800 to 1,100 feet west of the published boundary and return no hits against it, while a downtown control returns one. We confirmed it a third way by subtracting two per-folio tax totals, which produces exactly 0.3800. So the rate here is 19.9544 rather than 20.3344, worth about $149 a year on the median unit.
What will a unit cost to own each year?
On the median unit value in the completed first phase, about $391,810, roughly $7,818 a year without homestead and about $6,967 with it, plus nothing in non-ad-valorem assessments, which we proved against two non-zero controls. Homestead saves about $850.96, which at this price point is about 10.88 per cent of the bill, the best ratio of any Miami condominium page we have built. None of that includes association dues, which are not a public record at any stage.
How many owners actually live in the first phase?
None, on the record. Of 125 unit folios in the completed first phase, exactly zero carry a homestead exemption, against controls of 15.6 per cent and 24.8 per cent at two other Brickell buildings. Between 84 and 86 per cent are held by limited liability companies. Part of that is structural, because the fifty lodging units legally cannot be homesteaded at all. The rest is what it looks like. Read the declaration's rental provisions closely and understand that your neighbours will mostly be operators rather than residents.
Be first in line
Get on the Smart Brickell III interest list
We will connect you with a real estate professional licensed in Florida who represents you rather than the seller, who can register you before your first contact with the sales gallery, and who will get you the answers this page could not: how many condominiums this tower will be split into, who owns and maintains the podium and garage, the shared-facilities agreement, the proposed budget and reserve schedule, whether a specific unit is residential or lodging, the expected turnover date, and pricing and release timing as soon as they exist.
It costs nothing, creates no brokerage relationship by itself, and does not obligate you to anything.