Greenway Reserve

55 approved homesites at NE 25th Avenue, inside Ocala city limits

The city council rezoned this land in November 2024, approved the subdivision plan in October 2025, the water management district issued the site work permit in December 2025, and the county assigned the street addresses in late September 2026. No plat has recorded, no homebuilder has been named by anybody, and no price exists. It is a 55-lot subdivision on about twelve and a half acres under two miles from downtown Ocala, on high ground mapped outside the flood hazard area, with no community development district. Here is the record, including the commute question the city never studied.

Homes
55 detached
Inside city
Yes, Ocala
Flood
Mapped outside
Builder
None yet

At a glance

Greenway Reserve fast facts

Everything below comes from the city's adopted ordinances and resolutions, its council and planning commission records, the approved conceptual subdivision plan, the regional water management district permit file, the county appraisal, subdivision and addressing records and the federal flood mapping for this land, read in October 2026. Where a line is marked unresolved we could not establish it, and we are not going to guess.

Area
North-east corner of NE 25th Avenue and NE 28th Street, north-east Ocala
Jurisdiction
Inside City of Ocala limits, annexed in 2005. Not unincorporated Marion County
Status
Rezoned, plan approved, site work permitted and addressed. No plat recorded, nothing built
Homes
55 detached single-family homes for sale
Lot size
About forty feet wide by one hundred and ten feet deep, roughly 4,400 square feet
Size
About twelve and a half acres
Density
About four and a third homes to the acre
Streets
NE 26th Avenue, NE 27th Avenue, NE 29th Place, NE 29th Lane and NE 30th Lane
Addressed
Yes, in late September 2026. Eleven street segments were assigned to this subdivision
Rezoning
Adopted by the city council in November 2024, from institutional to planned development
Plan approval
The conceptual subdivision plan was approved by the planning commission in September 2025 and by the city council in October 2025
Site work permit
Issued. The water management district issued an individual permit for this site in December 2025, running to 2030
Recorded plat
None. The parcel is still one undivided tract and no lots exist yet

Unresolved. Get notified

Access
Primary access from NE 25th Avenue. The NE 28th Street connection is for emergency use only
Open space
About forty-five per cent provided against forty per cent required, including a small amenity tract
Internal roads
About half a mile, publicly maintained by the City of Ocala, as are water and sewer
Perimeter walls
Shown on the approved plan around the site
Concurrency
Not yet granted. The approved plan states so explicitly and defers it to later review
Community development district
None covering this parcel. Stormwater, drainage and the amenity tract are association funded
Homeowners association
Yes. It will own and maintain the retention areas, the drainage outside public right of way and the amenity tract
Flood
The whole parcel is mapped outside the special flood hazard area, on an upland site around seventy-five to eighty-three feet of elevation
Impact fee on record
A solid waste fee of 265 dollars per buildable lot, due when the council approves the final plat
School district
Marion County Public Schools, a single countywide district
Builder
None. No homebuilder has been named in any public record or any marketing

Unresolved. Get notified

Developer
Reported in local coverage as Boyd Real Estate Group. The owner of record is a single-purpose local company
Pricing, model home, sales centre
Unresolved. No price exists, no builder exists and no sales operation is open

Unresolved. Get notified

Floor plans and square footages
Unresolved. Nothing has been released

Unresolved. Get notified

Association dues
Unresolved. No figure is published

Unresolved. Get notified

City improvement plan
Unresolved. Reported as under city staff review in late 2025, and we could not reach a case record either way

Unresolved. Get notified

Developer agreement
Not yet on a council agenda. It must be approved and recorded before a final plat application is accepted

Unresolved. Get notified

Property tax rate
Unresolved. We did not pull the current city and county rates and will not estimate them

Unresolved. Get notified

ZIP code
Unresolved between 34470 and 34479. The boundary runs through this area and the tract has no situs address

Unresolved. Get notified

Whether dirt has moved
Unresolved. The permit authorises site work but no record confirms it has started

Unresolved. Get notified

Details on this page are compiled from public records and are targets, not commitments. Pricing, floor plans, home counts, and timing have not been released and are subject to change without notice.

Where it stands

Approved five times over, and still without a plat

The city council adopted an ordinance in November 2024 rezoning this land from institutional to planned development, and at the same meeting adopted the resolution approving the development plan and standards for it. The city's own zoning mapping independently carries that ordinance against this site, which is a useful cross-check rather than a formality. The standards book was then amended by a further resolution in the summer of 2025.

The subdivision plan itself was approved twice: by the planning and zoning commission in September 2025 and by the city council in October 2025, with the record showing it passed at both. Then the regional water management district issued an individual environmental resource permit for this site in December 2025, running to 2030. That is the permit that authorises the grading and the stormwater system. We checked the district's pending list separately, and this project is not on it, so there is no applied-for-but-unissued permit hanging over the site. Any one of these would be a real approval by a real agency; there are five.

And then the limitation that matters most: no plat has recorded, so the lots do not legally exist. We tested that three ways rather than trusting a name search. The county's current subdivision mapping, which we proved current by finding recordings from 2025 and 2026 in it, has no entry for this community. A point query of the site against that same mapping returns nothing. And most conclusively, the land is still a single undivided tract in the appraisal record, where a recorded fifty-five-lot plat would have created fifty-five separate parcels.

Two city steps stand between here and a plat. The improvement plan has to be approved, and a developer's agreement has to be approved by the council and recorded before a final plat application is even accepted. No developer's agreement has reached a council agenda. Worth knowing for anyone tracking this: Florida now processes final plats administratively with no public hearing, so there will never be an agenda item announcing it. The plat will simply appear in the records one day.

Subdiview is not affiliated with, endorsed by, or sponsored by Boyd Real Estate Group. Boyd Real Estate Group and its community names are trademarks of their respective owners and are used here for identification only. All community information is compiled from public records and is subject to change.

The question nobody studied

A two-lane road, a freight crossing and three subdivisions

If you read one section on this page, read this one, because it is the thing we would most want to know and it is checkable by anybody with a car and a morning. Everything leaving this subdivision goes out onto NE 25th Avenue, which is a two-lane road, and then south to the signals at NE 14th Street and Bonnie Heath Boulevard. On the way there is an active freight railroad crossing that closes for four minutes or more several times a day. The approved plan puts the primary access on NE 25th Avenue and makes the NE 28th Street connection emergency-only, so there is no second way out for ordinary traffic.

On its own that is a manageable quirk. The problem is cumulative. Two other residential subdivisions nearby were building at the same time this one was approved, one of them around a hundred units, and all three feed the same two-lane road. Each was individually small enough to fall below the city's threshold for a full traffic impact study, so none of them triggered one. This community's own approved plan counts about six hundred average daily trips and about fifty-eight in the evening peak hour, under the hundred-trip threshold, so only a brief traffic statement was required rather than a study.

A neighbour put exactly this to the city council in writing in September 2025, estimating roughly two hundred additional vehicles in the morning hour once all three communities are occupied, and asked the city to produce a cumulative study across them. Nothing in the public record shows one was ever done. We are not telling you the road will fail, and we are not going to pretend to model it. We are telling you that three approvals were each tested in isolation, that the rail crossing is real and documented, and that the city has not published an answer.

Drive NE 25th Avenue southbound at about half past seven on a weekday morning before you commit to anything here. It costs you twenty minutes and it is the single highest-value piece of diligence available on this community. One related thread worth following: the approved plan states in terms that this project has not been granted concurrency approval, deferring it to later review including building permit review, and concurrency is precisely the mechanism that tests whether roads have the capacity to serve new homes. So the traffic question is not formally closed.

We will tell you which builder buys these lots

That is the decision that settles the plans, the specification and the price here, and it gets made before anything is advertised. We will also flag the developer's agreement reaching the council and the plat recording. Nothing has been released, so there is no queue to lose a place in and no deposit to put down.

Get notified

What is actually being built

Small lots, high ground, and no builder yet

Fifty-five detached single-family homes for sale, on lots of about forty feet by one hundred and ten, which is roughly four thousand four hundred square feet each. The approved instrument is a subdivision plan creating fifty-five individually saleable lots served by public roads, public water and public sewer, which is what settles that this is for-sale product rather than a rental project under another name. Nothing in any record restricts occupancy by age. Density works out at about four and a third homes to the acre.

The plan puts about half a mile of internal roadway inside the site, and those roads along with the potable water and the sanitary sewer will be publicly maintained by the city, which is a better deal for a buyer than it sounds, because private road resurfacing is the largest bill an association ever faces. Open space comes in at about forty-five per cent against a forty per cent requirement, across five tracts, including an amenity tract of a little over a quarter of an acre. At fifty-five homes there is no economic basis for a clubhouse or a resort pool, so do not expect one. Perimeter walls are shown around the site on the approved plan.

The lots here are roughly four to five times smaller than the lots immediately across the property line. The site sits in a 1960s and 1970s large-lot city grid, and the abutting block to the east and south is made up of parcels of roughly four-tenths to just over half an acre carrying houses from the 1960s through the 2000s. That is not improper and it is how attainable new construction gets built inside an established city, but it does mean the product will read differently from its surroundings, the walls are doing real work, and the established neighbours have views about it, because the record shows they already do.

Nobody is building it yet, and that is a clean finding rather than a hole in our research. No homebuilder is named in any public record and no builder marketing exists anywhere. The owner of the land, which also holds the water management district permit, is a single-purpose local company that bought the site in December 2024, the month after the rezoning was adopted. Local news coverage from October 2025 reports the developer as Boyd Real Estate Group, which we pass on as reported in local coverage rather than as a record fact, because that name does not appear in any government document we reached. A fifty-five-lot subdivision inside city limits is the size that gets sold on to a regional builder, so expect the eventual brand to be one that does not exist here yet.

Water, taxes and dues

Mapped outside the hazard area, but inside the city

The whole parcel is mapped outside the special flood hazard area, and we established that by querying the federal flood mapping with the entire parcel outline rather than a single point, which matters because a point can sit clear of a hazard area that still clips part of a site. Exactly one flood area intersects this land, and it is the category the mapping describes as minimal hazard, with no base flood elevation assigned. The approved plan's own survey benchmarks put the site between about seventy-five and eighty-three feet of elevation, and the stormwater drains to a landlocked basin rather than to a river or lake. For a Florida site that is close to the best available answer.

For wider context rather than this site, the federal flood insurance programme records four claims across this whole county in 2026, two with a March loss date and two in June, and nineteen claims countywide in 2023 against eight in 2024, with none recorded for 2025 through the current data freeze and about one and a half million dollars paid countywide from 2020 onward. Those are county figures and say nothing specific about this parcel. A lender should not require flood insurance on a parcel mapped like this one, but get the confirmation in writing for your own lot once lots exist.

There is no community development district covering this parcel, which we confirmed against the city's own development agreements mapping at the site rather than by assumption; the one live district case in the city's planning records belongs to a different project. So no district assessment will appear as a second line on the tax bill, which is usually the most welcome thing a Florida buyer can hear. District coverage varies enormously across Florida and we are making a claim about this land only.

Now the cost that cuts the other way and is routinely missed. This site is inside city limits, annexed in 2005, so the tax bill carries the city municipal millage on top of the county, school and water management district levies. Comparable new construction out in unincorporated Marion County does not carry that city levy. We did not pull the current adopted rates and we will not estimate a tax figure without them, so treat that difference as a real question to price rather than a number we have handed you. Florida's additional homestead exemption is set statewide by Florida law rather than locally, and applies only from the January after you establish residency. One record-level fee worth knowing: a solid waste impact fee of two hundred and sixty-five dollars per buildable lot falls due when the council approves the final plat. On association dues, no figure is published and we will not invent one, but the association's job is defined: the retention areas, the drainage outside public right of way and the amenity tract. Ask who maintains the perimeter walls, because walls are expensive and long-lived and the answer is not always obvious.

Location and lifestyle

Under two miles from downtown, on city services

Downtown Ocala is under two miles south-west, which is most of the reason an infill site like this gets developed at all. The route out is NE 25th Avenue south to NE 14th Street and Bonnie Heath Boulevard, the state road that carries west toward the interstate corridor and the rest of the county. Being inside the city means city water, city sewer and city services rather than a well, a septic system and longer response times, which is a material difference from a good deal of the new construction going up in unincorporated Marion County.

Ocala's wider draw is horse country. The equestrian economy north and west of town is the reason this market exists at the scale it does, alongside a steady flow of retirees and remote workers priced out of central Florida. Immediately around this site the picture is more ordinary: an established residential grid, a church in the same envelope, and a proposed convenience store and fuel project at NE 35th Street whose site plan is pending resubmittal. Two nearby residential subdivisions were under construction as this one was approved, so expect construction traffic in the area for a while.

Schools are Marion County Public Schools, a single countywide district, and we deliberately name none. Assignment follows a specific address, the street segments exist but no lot or house does, and school capacity is one of the public facilities the deferred concurrency review will examine. Use the district's own locator once your address exists and get the answer in writing. The honest tradeoffs overall: this is a small subdivision on a two-lane road with a freight crossing, with small lots relative to its neighbours and a single modest amenity tract, and in exchange you get a new house inside city limits a couple of miles from downtown, on high ground, with no district assessment.

Buying new, with somebody on your side

What to settle before there is anything to sign

There is no builder here yet, let alone a sales operation, so nothing is urgent. That is exactly why it is the right moment to settle your own representation, rather than the moment you are standing in a finished model with a reservation form in front of you. You can have a real estate professional licensed in Florida on your side, touring with you, reading the contract line by line and pushing for every incentive, upgrade and closing-cost credit the builder will give, and on new construction the builder already budgets that fee whether you bring somebody or not. The catch is timing and registration: builders generally require your agent to be named from your first visit or first online registration, and if you register yourself first the agent usually cannot be added afterwards.

On a pre-construction purchase the contract mechanics are where the money is. Read the parts nobody reads: what happens to your deposit if the schedule slips, how long the builder may delay before you have a remedy, whether the price is fixed or subject to escalation, what the published specification includes as against what the model is finished with, and who administers the warranty. Four questions are specific to this community. What the plat finally shows for your lot's dimensions, since no plat exists today. Whether any conditions were attached at the improvement plan or concurrency stage that changed the layout. Who maintains the perimeter walls and the stormwater tracts, and what that does to the dues. And what the drive out onto NE 25th Avenue is actually like in the morning peak.

Then the ordinary discipline of buying new. Hire your own independent inspector at pre-drywall, again at the final walkthrough, and once more before the one-year warranty expires. Read the limited warranty booklet before you sign rather than after. We did not search Florida regulatory enforcement records or civil dockets for any builder, owner or entity connected to this community, so read the absence of any such note here as unchecked rather than clean.

Questions and answers

Greenway Reserve FAQ

Is Greenway Reserve actually approved?

Yes, five separate times over, and we want to be emphatic because this is the question we went in most sceptical about. The city council adopted an ordinance in November 2024 rezoning this land from institutional to planned development, and the city's own zoning mapping independently confirms that ordinance against this site. At the same meeting the council adopted a resolution approving the planned development plan and standards book for it, and it adopted an amendment to that book in the summer of 2025. The conceptual subdivision plan itself was then approved twice, by the planning and zoning commission in September 2025 and by the city council in October 2025, with the record showing it passed at both. And the water management district issued an individual environmental resource permit for this site in December 2025, which authorises the site work and runs to 2030. We checked the district's pending list separately and this project does not appear on it, so there is no applied-for-but-unissued permit hanging over the site. Each one of those on its own would be a real approval by a real agency. What has not happened is any home: no building permit in either jurisdiction, no plat, no builder.

Has a plat been recorded?

No, and this is the single most important limitation to understand about this community. We tested it three ways rather than trusting a name search, because that is the usual way to get this wrong. First, the county's current subdivision mapping, which carries recorded plat book and page references and which we proved is current by finding 2025 and 2026 recordings in it, has no Greenway Reserve at all. Second, a point query of the site against that same mapping returns nothing, meaning the site sits inside no recorded subdivision. Third and most conclusively, the land is still one undivided tract of about twelve and a half acres in the appraisal record. A recorded fifty-five-lot plat would have created fifty-five child parcels, and they do not exist. So the lots do not legally exist yet, the lot dimensions are not fixed on paper, and nothing here can be sold. Two city steps have to happen before a final plat can even be applied for: the improvement plan has to be approved, and a developer's agreement has to be approved by the council and recorded. Neither has happened.

What are the street names?

NE 26th Avenue, NE 27th Avenue, NE 29th Place, NE 29th Lane and NE 30th Lane, assigned across eleven street segments in late September 2026. We publish them, but we are going to be honest about their value in a way we would not be elsewhere. These are numbered grid names, continuing the existing Ocala street grid, rather than distinctive invented subdivision names. On most communities we write about, the street names are the single most useful thing we can give you, because nobody else has them and they are highly searchable. Here they are not, because dozens of unrelated existing addresses already sit on similarly numbered streets nearby. We did run a search on them specifically looking for a hidden builder brand, and found nothing but unrelated existing houses. What the addressing does tell you is real, though: the county formally assigned those eleven segments to this subdivision by name, which is independent confirmation that the project is live and moving rather than a paper approval sitting dormant.

What is the catch on the commute out of here?

This is the thing we would most want to know if we were buying here, and it is the question a builder's page will never answer. Everything leaving this subdivision goes out onto NE 25th Avenue, which is a two-lane road, and then south to the NE 14th Street and Bonnie Heath Boulevard signals. On the way there is an active freight railroad crossing that closes for four minutes or more several times a day. That alone would be a manageable quirk. The problem is cumulative. Two other residential subdivisions nearby were under construction at the same time as this one was approved, one of them around a hundred units, and all three feed onto the same two-lane road. Each of the three was individually small enough to fall below the city's threshold for requiring a full traffic impact study, so none of them triggered one. Greenway Reserve's own approved plan counts about six hundred average daily trips and about fifty-eight trips in the evening peak hour, under the hundred-trip threshold, so only a short traffic statement was required rather than a study. A neighbour wrote to the city council in September 2025 making exactly this point, estimating roughly two hundred additional vehicles in the morning school-and-work hour once all three are occupied, and asking the city to produce a cumulative study across the three. Nothing in the public record shows one was ever done. We are not telling you the road will fail. We are telling you nobody has checked, the rail crossing is real, and you should drive NE 25th Avenue southbound at half past seven in the morning before you commit to anything here.

What is immediately around the site, and how big are the neighbours' lots?

This is the second thing worth checking yourself, and it is unusually stark. The surrounding area is a 1960s and 1970s large-lot city grid. The block directly abutting this site to the east and south is made up of lots of roughly four-tenths to just over half an acre each, carrying houses built between the 1960s and the 2000s, valued broadly between the high one hundreds and the mid two hundreds of thousands. Greenway Reserve's lots are about forty feet by one hundred and ten, which is around four thousand four hundred square feet. That is roughly four to five times smaller than the lots immediately across the property line, and the approved plan shows perimeter walls around the site. Neither of those facts is hidden or improper, and small lots are how new construction gets built at an attainable price in an established city. But it does mean the product here will look and feel different from its surroundings, that the walls are doing real work, and that you should expect the established neighbours to have views about it, because the record shows they already do. Also in the same envelope are a church and a proposed convenience store and fuel project at NE 35th Street whose site plan is pending resubmittal.

Does it flood?

No, and this is the most reassuring answer on the page. We queried the federal flood mapping using the whole parcel outline rather than a single point, which matters because a point query can miss part of a site, and exactly one flood area intersects it: the whole parcel is mapped outside the special flood hazard area, in the category the mapping describes as minimal flood hazard, with no base flood elevation assigned. The approved plan's own survey benchmarks put the site at roughly seventy-five to eighty-three feet of elevation, which is high ground for Florida, and the stormwater system drains to a landlocked basin rather than to a river or a lake. That combination is about as good as a Florida flood answer gets. For context on the wider area rather than this site, the federal flood insurance programme records four claims across the whole of this county in 2026, two with a loss date in March and two in June, with the most recent month showing two. Looking back, the county recorded nineteen claims in 2023 and eight in 2024, with none recorded for 2025 through the current data freeze, and about one and a half million dollars paid across the county from 2020 onward. Those are countywide figures and not specific to this site. A lender should not require flood insurance on a parcel mapped like this, but confirm it in writing for your own lot once lots exist.

Is there a community development district, and what will the taxes be?

There is no community development district covering this parcel, and we checked the city's own development agreements mapping at the site rather than assuming. The one live district case in the city's planning records belongs to a different project entirely. So there will be no district assessment as a second line on the tax bill, which in Florida is usually the most welcome thing you can hear. Instead the association will own and fund the retention areas, the drainage outside the public right of way and the amenity tract, while the roads, water and sewer will be publicly maintained by the city, which is a better split for a buyer than it sounds. Now the part that cuts the other way, and it is routinely missed. This site is inside Ocala city limits, having been annexed in 2005, which means the tax bill carries the city municipal millage on top of the county, school and water management district levies. Comparable new construction in unincorporated Marion County does not carry that city levy. We did not pull the current adopted city and county rates, and we are not going to estimate a tax figure without them, so treat the city-versus-county difference as a real question to price rather than a number we have given you. Florida's additional homestead exemption is set statewide by Florida law rather than locally, and applies only from the January after you establish residency.

Who is building it?

Nobody yet, and that is an unusually clean answer rather than a gap in our research. There is no homebuilder named in any public record for this project and no builder marketing of any kind anywhere. The owner of the land, which is also the entity that holds the water management district permit, is a single-purpose local company that acquired the site in December 2024, the month after the rezoning was adopted. That is a land-development entity, not a consumer homebuilding brand. Local news coverage from October 2025 reports the developer as Boyd Real Estate Group, and we are passing that on as reported in local coverage rather than as a record fact, because we did not find that name in any government document we reached. The engineer who signed the approved plan is a local Ocala engineering firm based in the same address building as the owner company. What this means practically is that the most important single thing about this community, which is who will build the houses and to what specification and price, is genuinely undecided. A fifty-five-lot subdivision inside city limits is the size that gets sold to a regional builder rather than developed by a national one, so expect that, and expect the brand name on it to be something that does not exist yet.

What does it mean that concurrency has not been granted?

It is a real caveat and the approved plan states it in capital letters rather than burying it, so we will repeat it plainly: this project has not been granted concurrency approval, and that question is deferred to later review stages including building permit review. Concurrency is the Florida mechanism for confirming that public facilities, which in practice means roads, water, sewer, drainage, schools and parks, have the capacity to serve a development when it comes online. Deferring it is normal and it is not a sign of anything irregular. Plenty of approved plans carry exactly this note. But it matters here for two reasons. First, it is the formal hook on which the traffic question above could still be revisited, because capacity is precisely what concurrency tests. Second, it means that between today and a building permit there is still a review stage at which conditions can be attached, and conditions can change lot yields, road connections and timing. So when somebody eventually tells you this community is fully approved and ready to go, the accurate version is that the zoning and the plan are approved, the site work is permitted, and the capacity test and the plat are still ahead of it.

How far is it to downtown Ocala and the rest of the area?

Close, and this is a genuinely convenient location, which is most of the reason an infill site like this gets developed at all. Downtown Ocala is under two miles to the south-west, which is walking-adjacent by Florida standards and a very short drive. The route is NE 25th Avenue south to NE 14th Street and Bonnie Heath Boulevard, which is the state road that carries you west toward the interstate corridor and the rest of the county. Being inside the city means city water, city sewer and city services rather than wells, septic systems and longer response times, which is a material quality-of-life difference from much of the new construction going up in unincorporated Marion County. Ocala's wider draw is horse country, and the equestrian economy north and west of town is the reason this market exists at the scale it does, along with a steady flow of retirees and remote workers priced out of central Florida. The honest tradeoffs for this particular site: it is a small infill subdivision on a two-lane road with a rail crossing, not an amenity community, the lots are small relative to the neighbourhood, and the amenity provision is a single small tract rather than a clubhouse and pool. What you get in exchange is a new, code-built house inside city limits a couple of miles from downtown.

Which schools serve it?

This site is served by Marion County Public Schools, which is a single countywide district, and we are deliberately not naming individual schools. School assignment follows a specific address, and while the street segments here have been assigned, no lot and no house exists yet, so there is no address to run through an assignment tool. Beyond that, naming an elementary school on a page like this is the single most damaging error we could make, because a buyer makes a real decision on it and then discovers the boundary moved. Use the district's own school locator once your specific address exists, and get the answer in writing before you sign anything. Worth noting in passing that school capacity is one of the public facilities the deferred concurrency review will look at, so it is not an entirely settled question at the community level either.

What is the association going to cost?

No figure is published and we will not invent one. What we can tell you is precisely what the association is going to be responsible for, which is more useful at this stage than a number would be, because it tells you the shape of the eventual budget. The approved plan assigns the retention areas, the drainage outside the public right of way, and the amenity tract to the association to own and maintain. The amenity tract is small, a little over a quarter of an acre, so do not expect a clubhouse, a resort pool or a fitness centre on a community of fifty-five homes, because there is no economic basis for one. The roads, the potable water and the sanitary sewer will be publicly maintained by the city, which is genuinely good news: on many Florida communities the association carries private roads, and road resurfacing is the single largest line item an association ever faces. So the likely profile here is a modest assessment covering stormwater maintenance, the small amenity tract, landscaping, the perimeter walls and insurance. Ask for the budget, the dues schedule and the full declaration in writing, and ask specifically who maintains the perimeter walls, because walls are expensive and long-lived and the answer is not always obvious.

What could you not establish?

A handful of things, and we would rather list them than let silence imply we checked everything. We could not find the city improvement plan's case record or its approval status. The city's permit register sits behind an authenticated portal that refused our requests, and the two public mapping layers the city does publish, both of which we read in full, do not carry this project, although one of them is demonstrably a curated subset rather than a complete register. So that is a record we could not reach, not a finding that no improvement plan exists, and it is certainly not a finding that it was merely applied for. The last positive information on it is local coverage from October 2025 describing improvement plans as under city staff review. We also could not find any developer's agreement in any status, and that one is a genuine absence rather than an access problem, because a search of council matters returns only the two 2025 plan items, so no such item has reached an agenda. We could not establish a builder, any price, any floor plan, or any dues figure. We could not resolve whether the correct ZIP code here is 34470 or 34479, because the boundary runs through this area and an undeveloped tract has no situs address. We did not pull current millage rates, so we state no tax figure. And we did not inspect recent aerial imagery, so whether earth has physically moved on the site since the permit issued in December 2025 is unknown to us: the permit authorises it, and no record confirms it has started.

Why join a list this early?

Because on this community the single most consequential fact, which is who builds the houses, has not been decided yet, and that decision will be made before anything is advertised. The sequence from here is fairly predictable: the improvement plan gets approved, a developer's agreement goes to the council and gets recorded, the final plat is processed administratively with no public hearing, and somewhere around there the lots get sold to a builder, who brings a brand, a plan set and a price list. By the time there is anything to look at, the product decisions are already made. Joining a list now costs nothing, puts no deposit at risk and creates no obligation. What it does is put you in front of a real estate professional licensed in Florida who represents you rather than the seller, before you ever put your own name on a builder's registration form, which is the one step in this whole process that is genuinely hard to undo afterwards.

Be first in line

Get on the Greenway Reserve interest list

We will connect you with a real estate professional licensed in Florida who represents you rather than the seller, who can arrange your representation before you put your name on any builder's registration form, and who will chase the answers this page could not: which builder buys these lots, what the improvement plan and the developer's agreement end up requiring, what the recorded plat shows for lot dimensions, the association dues, and the first published price.

Nothing has been released for this community yet and no price exists. Get notified when a builder is named, the developer's agreement reaches the council, or the plat records. It costs nothing, creates no brokerage relationship by itself, and does not obligate you to anything.

Subdiview is operated by a real estate broker licensed in Illinois. We are not your agent, we do not represent you, and we perform no real estate brokerage services in this state. No one at Subdiview is licensed in this state. If you join an interest list, your information is referred to a real estate professional licensed in the state where the property is located, who will contact you directly. We are compensated by that professional's brokerage, not by you.

Joining the interest list is free, creates no brokerage relationship, and does not obligate you to anything. Subdiview is operated by a real estate broker licensed in Illinois and is not licensed in Florida. Your information is referred to a real estate professional licensed in Florida, who will contact you directly and can register you as represented before your first visit to a sales office.

Subdiview is operated by a real estate broker licensed in Illinois. We are not your agent, we do not represent you, and we perform no real estate brokerage services in this state. No one at Subdiview is licensed in this state. If you join an interest list, your information is referred to a real estate professional licensed in the state where the property is located, who will contact you directly. We are compensated by that professional's brokerage, not by you.

Subdiview is not affiliated with, endorsed by, or sponsored by Boyd Real Estate Group. Boyd Real Estate Group and its community names are trademarks of their respective owners and are used here for identification only. All community information is compiled from public records and is subject to change.

Details on this page were read in October 2026, are as adopted, approved or issued rather than as offered for sale, and are subject to change. Flood mapping and claims figures carry the data release dates stated above. We did not search civil dockets.